Vadodara–Mumbai Expressway Status: What's Open in Late 2026

The Vadodara–Mumbai Expressway, the southern half of NE-4, is in three very different states at once. In Gujarat, the seven packages from Vadodara to Kharel near Navsari are open. The next 90 km, to the Maharashtra border, has barely been built. And in Maharashtra, the stretch from Talasari to Virar was nearly finished in May but we can't find any confirmation that it has opened.

That means you can drive from Vadodara to Surat and beyond on the expressway today, but not to Mumbai.

The section is about 448 km in all: 277 km from Vadodara to the Gujarat–Maharashtra border, 79 km on to Virar, and 92 km from Virar round the east of Mumbai to the port at JNPT, according to the expressway's Wikipedia entry.

Vadodara to Kharel: open

| Packages | Stretch | Opened | |---|---|---| | 1–3 | Vadodara–Bharuch | February 2024 | | 4–7 | Bharuch–Kim–Ena–Kharel | Phased, completed on a trial basis in January 2026 |

Swarajya reported on 15 January 2026 that with Package 7 opened, all seven packages were operating and the road was continuous from Vadodara to Kharel. Packages 5 and 7 opened on trial, with some stretches open on one side only and a few diversions.

The section crosses the Narmada on India's longest extradosed cable-stayed bridge. Interchanges serve NE-1 to Ahmedabad (at Dodka), NH-48 near Nandesari, the Padra road, Dahej (SH-6), NH-48 at Moti Naroli near Kim, and Surat via NH-53 at Ena.

Unusually for NE-4, the tolls on this stretch are published. DeshGujarat printed the car rates in January 2026:

| Car, single journey | Gandeva | Ena | Moti Naroli (Kim) | |---|---|---|---| | From NE-1 (Vadodara) | ₹480 | ₹400 | ₹305 | | From Moti Naroli (Kim) | ₹175 | ₹95 | | | From Ena | ₹80 | | |

Return journeys are charged at one and a half times the single toll. On 21 July 2026, rates at the four Vadodara district plazas went up by around 5%, DNP India reported: Dodka to ₹210 for a car, Fazalpur to ₹200 and Samiyala to ₹130, with Sampa unchanged at ₹90.

Near Ankleshwar, quality has been a recurring problem. NHAI repaired cracks on the Kim–Bharuch stretch in March; a bridge deck gave way between Adol and Piludra in July; and in October, Gujarat Samachar reported that deteriorated concrete panels were being torn up and relaid, with Bharuch-to-Surat traffic squeezed into two lanes. Our quality issues story covers the July incident.

Kharel to the Maharashtra border: stalled

Packages 8, 9 and 10, from Gandeva to Talasari, are about 90 km and years behind. Package 8 was on its fourth tender in October. Package 9 went to Ashoka Buildcon on 9 November. Package 10's future was unclear. A Times of India report in October said a nonstop drive to Mumbai might not happen before December 2029. The full story is in our piece on the stalled Gujarat packages.

Talasari to Virar: built, not confirmed open

DeshGujarat's January 2026 update on Maharashtra put Package 11 (Dahanu–Talasari) at 100%, Package 12 (Palghar–Dahanu) at about 91% and Package 13 (Virar–Palghar) at about 89%. The Palghar interchange was finished, toll structure included. Two things were left: one side of the Virar interchange, and a second bridge over the Vaitarna river.

In May, Infra News India, an infrastructure-tracking account, said only the Vaitarna bridge was pending and that all three packages could open in four to five months. That would have been September or October.

We haven't found a report that it has opened. And even when it does, it won't connect to the rest of NE-4 until Packages 8 to 10 are built. It will work as a fast road between Talasari and Virar for the Mumbai region, and that's all.

Virar to JNPT: the missing link

The 92 km Virar–JNPT section runs east of Mumbai through Vajreshwari, Amane and Badlapur. It was under construction as of March 2026, according to Wikipedia.

Its end at the port has its own gap. The plan was to reach JNPA through MSRDC's Virar–Alibaug multimodal corridor, but that project has stalled. So NHAI decided to build a new 15 km link from Morbe to the Kalamboli junction, at around ₹9,000 crore, the Free Press Journal reported in December 2025, citing Loksatta. NHAI regional manager Anshumali Srivastava said it would bring JNPA within 20 to 25 minutes. Until then, NHAI's plan was to open only as far as Raite, about 140 km from Talasari, leaving a long detour to the port.

Driving to Mumbai today

Use NE-4 from Vadodara to Kharel near Gandeva, then NH-48 through Valsad and Vapi into Mumbai. Our Mumbai to Delhi route guide covers the trip in the other direction.


Sources: Swarajya, 15 Jan 2026; DeshGujarat, 14 Jan 2026; DNP India, 21 Jul 2026; Gujarat Samachar, 7 Oct 2026; DeshGujarat, 21 Jan 2026; Infra News India on X, May 2026; Free Press Journal, 9 Dec 2025; Bombay Samachar, 18 Oct 2026; Wikipedia, Delhi–Mumbai Expressway.