The longest-running Delhi–Mumbai Expressway delay is about 90 km of road in south Gujarat. Packages 8, 9 and 10 run from Gandeva in Navsari district to the Maharashtra border near Talasari, and all three were awarded to the same Pune company. Package 8 was first awarded in 2021. Five years on, the most advanced of the three is about a third built.
On 18 October, Bombay Samachar, citing the Times of India, reported that a nonstop drive from Delhi to Mumbai "may have to wait until December 2029." The government's target is earlier.
This post goes package by package, using the most recent figures we could find.
The three packages
| Package | Section | Length | Progress | Status, mid-November 2026 | |---|---|---|---|---| | 8 | Jujuwa–Gandeva, km 154.6 to 190.0 | 35.4 km | 4.85% | Fourth tender; bids closed 13 October | | 9 | Karvad–Jujuwa, km 128.0 to 154.6 | 26.6 km | about 22% when terminated | Ashoka Buildcon issued Letter of Acceptance, 9 November | | 10 | Talasari–Karvad | 24.6 km | 36.23% | Reports differ |
The progress figures are from Construction World on 28 October. DeshGujarat's April roundup had about 5%, 10% and 42–43%. Package 9 rising from 10% to 22% is plausible. Package 10 falling from 42% to 36% isn't, so one of the two outlets is measuring it differently, and neither explains its method. Our construction tracker currently shows the April-style figures.
One contractor, three packages
Roadway Solutions India Infra Ltd (RSIIL), based in Pune, held all three. Construction World's account of Package 8 shows how it came apart:
- 2021: awarded to RSIIL under the hybrid annuity model, where NHAI pays part of the cost during construction and the rest in instalments over the following years.
- March 2023: NHAI terminated the contract after delays.
- November 2023: re-awarded to RSIIL, this time as a straight EPC (engineering, procurement and construction) contract.
- January 2026: terminated again. At a Delhi High Court hearing on 13 January, the court noted that most of the land had been handed over and that the contractor had missed its milestones, and allowed NHAI to bring in someone else, DeshGujarat reported.
RSIIL's case was that incomplete land acquisition caused the delays. NHAI officials told the Times of India the contracts were ended because RSIIL missed milestones despite several extensions. Bombay Samachar says NHAI has since blacklisted the company.
Package 8: four tenders and a walkaway
NHAI re-tendered Package 8 in January 2026 at an estimated ₹1,475.68 crore, with two years to finish, according to DeshGujarat. Nine companies bid, RSIIL among them. Four, RSIIL included, were knocked out at the technical stage. Five reached the financial round: Bansal Construction Works, Ashoka Buildcon, Ceigall India, G R Infraprojects and Kalthia Engineering.
Bansal came in lowest, more than 10% under NHAI's estimate. Then it refused the award.
NHAI cashed its bid security of ₹14.76 crore, Construction World reported. Officials quoted by the Times of India called this unprecedented. Bansal gave no reason.
Nobody has explained it since.
So NHAI started over. The fourth attempt to find a contractor went out on 14 September with bids due on 13 October, and Bombay Samachar reported seven bids received. We haven't seen an award.
Package 9: a new contractor
This is the one piece of good news. Ashoka Buildcon submitted its bid on 5 November, was named lowest bidder, and told the stock exchanges on 9 November that NHAI had issued it a Letter of Acceptance. The contract is for the balance work on the 26.6 km Karvad–Jujuwa section, worth ₹865.90 crore before GST, on EPC terms, Business Today reported on 10 November.
Bombay Samachar had reported that RSIIL bid for Package 9 despite the blacklisting, and challenged NHAI's eligibility rules in court. The Delhi High Court let NHAI keep evaluating bids. The award to Ashoka suggests the case didn't hold things up, though we haven't seen a final ruling.
Package 10: unclear
The 24.6 km Talasari–Karvad package is the furthest along. The two latest reports disagree on what happens next. Construction World said on 28 October that it "faces potential termination" over poor performance. Bombay Samachar said NHAI was at the final stage of appointing a replacement contractor. Neither gave a date.
Which deadline to believe
| Source | Date given | |---|---| | Nitin Gadkari, Lok Sabha, Feb 2026 | Financial year 2027–28, so by March 2028 | | DeshGujarat, Apr 2026, citing Gadkari | April 2028 | | Construction World, 28 Oct 2026 | 30 June 2028, revised deadline for the whole expressway | | Bombay Samachar and Times of India, 18 Oct 2026 | December 2029 for the nonstop drive |
Our own reading: Package 8 had 4.85% of its work done and no contractor in mid-November. NHAI's January tender gave the winner two years. If a new contractor starts in early 2027, that puts completion in early 2029 at best, before any slippage. The December 2029 figure looks closer to reality than March 2028.
That's our inference from the published numbers, and NHAI hasn't said anything like it.
If you're driving to Mumbai now
The expressway's southern end is the Kharel interchange near Gandeva in Navsari district. From there, Mumbai-bound traffic uses NH-48 through Valsad and Vapi to the Maharashtra border. On the evidence above, that NH-48 stretch will stay part of the trip for at least two more years.
Our Mumbai to Delhi route guide covers the rest of the drive, and the completion date explainer has the full timeline for every section.
Sources: Bombay Samachar, 18 Oct 2026, citing the Times of India; Construction World, 28 Oct 2026; DeshGujarat, 6 May 2026; DeshGujarat, 16 Apr 2026; DeshGujarat, 13 Feb 2026; Business Today, 10 Nov 2026.