Ask what the Delhi–Mumbai Expressway cost and you'll get at least five answers, all from official or near-official sources. Our own homepage says about ₹1,00,000 crore. Nitin Gadkari has given three different figures in the past year, two of them to Parliament.
None of them has to be wrong. They count different things, at different dates.
The figures, in order
| When | Figure | Who said it, and what it covers | |---|---|---| | March 2022 | ₹87,453 crore, estimated | Reported at DME Development Ltd's first bond issue (Swarajya) | | Long-standing | about ₹1,00,000 crore, including land | The expressway's Wikipedia entry; also the figure on our homepage | | December 2025 | ₹1.04 lakh crore total; ₹71,718 crore spent | Gadkari, written reply in the Rajya Sabha winter session (DeshGujarat) | | 25 March 2026 | ₹96,547 crore sanctioned; ₹77,558 crore spent up to December 2025 | Gadkari, written Rajya Sabha reply (Swarajya, Business Today) | | 8 July 2026 | ₹1.10 lakh crore; 75–80% complete | Gadkari, public meeting at Mandana near Kota (Business Today) |
Construction World repeated the ₹1.04 lakh crore and ₹71,718 crore figures, dated to December 2025, on 28 October 2026.
Why they don't match
Three things move the number.
The first is scope. Gadkari's March reply covered 54 packages and 1,445 km, spurs included. Wikipedia describes 1,350 km in 52 packages. His December reply used 1,386 km. Every spur or link road added to the scheme adds to the total.
The second is land. Wikipedia's ₹1,00,000 crore explicitly includes land acquisition. The 2022 figure may or may not; Swarajya's report didn't say. Land was a big share of the early money. By January 2021, NHAI had spent about ₹9,500 crore on land and pre-construction work, against about ₹7,300 crore on construction itself.
The third is the word "sanctioned." ₹96,547 crore is the sanctioned cost. The ₹1.04 lakh crore and ₹1.10 lakh crore figures are given as the total, with no breakdown. The gap between them is ₹7,453 crore to ₹13,453 crore, and no report we found explains it.
Spending is the odd one out. December's reply said ₹71,718 crore had been spent. March's said ₹77,558 crore up to December 2025. If both describe roughly the same date, they're ₹5,840 crore apart. DeshGujarat's account of the December reply gives no as-of date, so its number may be from earlier in 2025.
Cost per kilometre
Our own rough sums, nothing official: ₹96,547 crore over 1,445 km comes to about ₹67 crore a kilometre. ₹1.10 lakh crore over 1,386 km comes to about ₹79 crore. Pair the figures differently and you land somewhere in between.
Both figures include interchanges, bridges, the Mukundra tunnel and the spurs, so they say little about what a plain stretch of eight-lane road costs.
How it's paid for
NHAI set up a wholly owned company, DME Development Ltd (DMEDL), on 29 August 2020 to raise money for the expressway. NHAI collects the tolls. DMEDL receives annuity payments from NHAI and carries no construction or toll-collection risk, according to the expressway's Wikipedia entry.
DMEDL borrows from banks and the bond market. Its first bond issue, in March 2022, raised ₹5,000 crore over 15 years at 6.85%, Swarajya reported. The money was for the Delhi–Vadodara section's construction contracts and the upfront payments on the Vadodara–Mumbai section's hybrid annuity contracts.
Two later moves made the financial press. In December 2024, DMEDL raised ₹775 crore through green bonds, which Business Standard reported as the first such issue in the roads sector. In November 2025, Business Standard reported that it planned to buy back ₹5,975 crore of its bonds.
Delay and the bill still to come
The same 2022 bond report gave March 2023 as the target for the Delhi–Mumbai stretch and September 2023 for the JNPT spur. More than three and a half years past the first of those dates, the biggest open item is the 90 km of stalled packages in south Gujarat.
Their re-tenders show some of the money still to be committed. Package 8's remaining work was estimated at ₹1,475.68 crore in January 2026, and Ceigall India's financial bid was ₹1,581 crore, according to Construction World. Package 9's balance work went to Ashoka Buildcon in November for ₹865.90 crore before GST.
We haven't found the original 2021 contract values for these packages published, so we can't say how much the delay itself has added.
What to watch
Updated sanctioned-cost and spending figures have tended to appear in Gadkari's written replies to Parliament. The next set will probably come in the winter session. Our completion date explainer tracks the timeline side of the same story.
Sources: Swarajya, 17 Mar 2022; DeshGujarat, 18 Dec 2025; Swarajya, Mar 2026, on Gadkari's Rajya Sabha reply; Business Today, 4 Nov 2026; Business Today, 9 Jul 2026; Construction World, 28 Oct 2026; Business Standard, Dec 2024; Business Standard, Nov 2025; Wikipedia, Delhi–Mumbai Expressway.