DND–Jaitpur Stretch: How NE-4 Now Starts Inside Delhi

Since 23 August 2026, you can get onto the Delhi–Mumbai Expressway without leaving Delhi. NHAI opened the 9 km DND–Jaitpur stretch on a trial basis that day, linking the DND Flyway at Maharani Bagh to Jaitpur on the Delhi–Faridabad border. Before that, the Delhi arm of NE-4 began at Jaitpur, and anyone coming from south or east Delhi had to fight through Mathura Road or Kalindi Kunj traffic to reach it.

The first three months haven't been smooth. In about five weeks the stretch opened, closed, partly reopened, closed again and got extra safety work.

What the 9 km covers

About 8.5 km of the 9 km is elevated, DNP India reported on opening day. The road starts where the DND Flyway meets Ring Road at Maharani Bagh. It runs south past Khizrabad, Batla House and Shaheen Bagh on the Yamuna's west bank, then follows the Agra Canal from near Okhla Vihar metro station to Mithapur, and leaves Delhi near the MCD toll at Mithapur Chowk.

There are two ramps along the way, at Jaitpur and Meethapur. Both were kept shut during the trial. A further ramp near Kalindi Kunj metro station, for traffic coming from Noida, is in the plan but hasn't been reported open.

South of Jaitpur the road was already running. Of the 59 km link between the DND Flyway and the main expressway, about 50 km had opened in phases by August, News24 reported, with the Jaitpur–KMP part fully operational. The Jaitpur to Faridabad Sector 65 section opened back in November 2024. Our construction tracker lists the Delhi arm as three packages: this 9 km piece, then 25 km and 26 km sections through Faridabad.

From trial to reopening, August to September

| Date (2026) | What happened | Reported by | |---|---|---| | 23 Aug | Trial opening, 40 km/h limit, Jaitpur and Meethapur ramps closed | DNP India, News24 | | By 31 Aug | Elevated section shut again after Delhi Police complaints | Construction World | | Night of 1 Sep | Delhi-bound carriageway, Jaitpur to Maharani Bagh and Sarai Kale Khan, opened | Urbanacres, citing Live Hindustan | | September | Jams near Sarai Kale Khan; traffic police had the Jaitpur–Sarai Kale Khan route closed | Urbanacres | | By 30 Sep | Reopened after NHAI laid rumble strips near Maharani Bagh, the Ashram flyover and the Sarai Kale Khan loop | Urbanacres |

The reason given for the August closure was the merge point, not the road itself. Construction World said the spot where expressway traffic drops into city traffic had no warning signs, rumble strips or speed breakers. NHAI's project director said those were being put in inside the Delhi border, and that the Faridabad-to-Delhi direction should reopen within two or three days. Urbanacres later reported that the Delhi-bound carriageway opened on the night of 1 September.

The Ashram end is still disputed. Delhi Traffic Police and NHAI disagree about whether that junction is safe, and we've covered the argument separately in the Ashram junction story.

Who gains

Mostly people in south and east Delhi, Noida and Ghaziabad.

Someone near Lajpat Nagar heading for Jaipur used to reach the expressway one of two ways: thread through Kalindi Kunj or Mathura Road traffic to the old start at Jaitpur, or cross to Gurugram and join at Sohna. Now they can get on at Maharani Bagh.

DNP India listed the expected benefits on day one as easier access towards Jaipur and Sawai Madhopur, and less pressure on the Ashram, Kalindi Kunj and Mathura Road routes. Construction World added residents of New Friends Colony, Sukhdev Vihar and Kalindi Kunj to the list.

Faridabad gets the reverse benefit. News24 quoted an expected 20 minutes from Faridabad to the DND Flyway, a figure given before the closures and the rush-hour trouble.

Driving it now

The trial limit was 40 km/h. We haven't seen a later notice raising it, so expect a low limit on the elevated section.

Rush hour at the Ashram end is the weak spot. NewsX reported on 29 September that two traffic officers are posted at the junction during peak hours because expressway traffic arrives fast and without a break.

Check the Jaitpur and Meethapur ramps before relying on them. They were shut during the trial and we haven't found confirmation that both are open now.

Past Jaitpur, the road runs through Faridabad and Ballabhgarh, crosses the Palwal–Sohna road at Hajipur and reaches the toll plaza at Kiranj in Nuh district, about 56 km from the DND start. Soon after, it joins the main expressway at the KMP interchange. Our entry and exit points page lists every ramp beyond that.

What's still pending

Union minister of state Krishan Pal Gurjar said the formal full opening would probably follow an inauguration by the Prime Minister, according to News24. No date has been given. Until then, the stretch is open but unsettled. It has already closed at short notice twice.

The other Delhi-area link under construction is the spur from Faridabad Sector 65 to Noida International Airport at Jewar. The Union Cabinet approved a revised cost of about ₹3,630 crore for it in March 2026, including an 11 km elevated section between Faridabad and the airport. It isn't open.


Sources: DNP India, 23 Aug 2026; News24, 23 Aug 2026; Construction World, 31 Aug 2026; Urbanacres, 30 Sep 2026, citing Live Hindustan; NewsX, 29 Sep 2026; PIB, Cabinet approval of the Jewar link, Mar 2026; Wikipedia, DND–KMP Expressway.